Bridge work in Bürstadt: B 47 blocking for a better driving experience!

Bridge work in Bürstadt: B 47 blocking for a better driving experience!

In Bürstadt, the repair work on the bridge over the B 47 is in the last trains. Like hessen.de , the work is scheduled for the residents and travelers.

In the next week, on April 15 and 16, however, the B 47 will be closed. This measure will come into force during the day between 9 a.m. and 3 p.m. and takes place to remove the scaffold below the bridge. A construction site lamp is used for the traffic regulation to ensure flowing traffic.

scope of the repair measures

The repair work included a number of extensive measures to make the bridge more secure and more functional. The road as well as the caps and coverings were torn down and renewed above the bridge. The bridge inlets and seals also received a refreshment. Furthermore, new connection reinforcements and transition constructions were installed on both sides. The railing was also renewed and a embankment staircase was restored.

Below the bridge, numerous damaged areas were repaired in the concrete. Cracks were closed, and exposed reinforcing parts were rusted and renewed. In addition, the bridge drainage was optimized by installing a new steel line. According to Mannheimer-morgen.de Return transport of the scaffolding materials.

financing and future use

The total costs for the repair amount to around 816,000 euros, which are financed by the federal government. The planned traffic release of the bridge is scheduled for April 24, matching the popular asparagus hike, which attracts many participants in the region.

With this bridge, the new “Sonneneck” development area directly connects to the city center of Bürstadt, which significantly improves the mobility of the residents. The regular exams had previously determined damage and defects in the bridge, which underlines the urgency of these repair work.