Massive railway restrictions: commuters between Offenbach and Frankfurt!

Massive railway restrictions: commuters between Offenbach and Frankfurt!
commuter between Offenbach and Frankfurt must adapt to massive restrictions in S-Bahn traffic. From April 28, 2025, extensive construction work begins in the Offenbach City tunnel, which will last until October 20, 2025. The main goal of this work is the renewal of rails, the course and an increase in fire protection measures. These comprehensive measures lead to considerable disabilities and sometimes complete closures of the route, especially between Offenbach-Ost and Hanau Central Station.
like fnp.de reports on April 28 and lasts until May 6, 2025. During this time the route between Offenbach-Ost and Hanau Central Station on three nights - from April 28th to 30th and on May 5th and 6th - fully blocked from 00:20 to 04:20. In addition, there are no trains in the section mentioned during the day between the 1st and 4th May. During this time, the S8 will only run between Wiesbaden and Frankfurt Central Station, while the S9 between Wiesbaden and Offenbach Ost drives through the tunnel. A replacement rail traffic between Offenbach Ost and Hanau is set up.
construction phases and their effects
The second construction phase begins on May 7th and 8th, 2025 and extends until the beginning of July 2025. Here, the route between Offenbach Ost and Frankfurt-Mühlberg will be affected. In the nights from Monday to Tuesday and Thursday to Friday, only one track will be accessible, while between 0:20 a.m. and morning hours there is a complete block. Complete closures are also planned on weekends.
As soon as the third construction phase is due, the entire S-Bahn connection between Offenbach Ost and Frankfurt-Mühlberg is blocked. For the period after the autumn holidays, further nocturnal restrictions and a complete lock of the section are planned. Deutsche Bahn has announced that the traffic should be recorded regularly after the work has been completed.
But the construction work is not only in the Offenbach City tunnel. As well as FAZ.net Frankfurter S-Bahn tunnel. This construction work is on schedule after more than three years and lead to a full blocking of the tunnel for six weeks. A new electronic signal box is installed to improve punctuality. These measures also lead to restrictions in the unearthly S-Bahn traffic, while replacement buses have been set up, which do not start the Taunus, main guard, Konstablerwache, Ostendstraße and local train station.
The information on these comprehensive construction work and its effects on rail traffic are also available on sbahn.berlin . Commuters are urgently asked to find out about the changes before traveling to avoid inconvenience.